This year's first production well № 1.321 was built in the Balkan velayat on the Barsagelmes area, which has already been handed over to the oilmen of the Nebitdag Drilling Department Nebitdagburawişmüdirligi.
The oil-bearing well was drilled ahead of schedule, its target depth is 1900 meters.
Experts determine the composition of hydrocarbons, the potential, the flow rate of a well ready for development, so that the oilfield workers can start production.
In total, 14 drilling crews work in Nebitdagburawişmüdirligi, reported on the “Neutral Turkmenistan” newspaper.